"To-date the developer has not started construction of the project." That is the City of El Segundo's own status line for Pacific Coast Commons, the 263-home mixed-use plan along Pacific Coast Highway that the City Council approved on March 15 and April 19, 2022. This post publishes in the last week of October 2026, about four and a half years after that vote. The site is still waiting.
If you're comparing South Bay cities, you may have read that El Segundo rezoned land for housing and approved new projects, and figured more inventory is on the way. Those approvals are real. The catch is in where the new homes would go and what kind of homes they are. Almost everything in El Segundo's pipeline is apartments or mixed-use buildings on commercial corridors. City leaders have also said they don't want more density in the residential neighborhoods. For a buyer looking at single-family homes, the projects in the pipeline offer almost nothing new.
Here is every residential project on the City's approved and pending lists, along with its current status.
| Project | Homes | Where it stands |
|---|---|---|
| Pacific Coast Commons, PCH between Holly Ave and Palm Ave | 257 apartments, 6 townhomes | Approved 2022; construction not started |
| 201–209 Richmond Street, Downtown | 6 third-floor homes | Approved July 10, 2025; plans under review, building permit pending |
| Grand/Kansas Specific Plan, 1521 E. Grand Avenue | 276 apartments | Application incomplete; EIR in preparation |
| 703 N. Pacific Coast Highway | 79 rental units | Application submitted |
| 455 Main Street | 4 units | Application incomplete, pending resubmittal |
Add it up and the pipeline holds more than 600 homes. That's more than El Segundo's entire state housing target for the current cycle, which is 492 units: 189 very-low-income, 88 low-income, 84 moderate-income and 131 above-moderate-income. Not one of the five projects in that table shows construction underway.
Look at the mix, too. About 610 of those homes are apartments or rentals. The townhome count is six. Pacific Coast Commons does include 32 affordable units across its two apartment buildings. Even if every project were finished tomorrow, someone shopping for a detached house with a yard would find almost nothing new to bid on.
When Urbanize LA covered the 2022 approval, it named the developer as a joint venture of Mar Ventures, Inc. and Continental Development Corporation and reported an expected construction period of 34 months. At that pace the buildings would be finished by now. The site has no shovels in it.
A City contract record lists Development Agreement 6412 for the project as current through April 19, 2037. Nothing on the City's project page says when construction will start.
Smaller projects stall too. The Richmond Street project downtown is two three-story buildings with ground-floor retail and office space and six homes on the top floors. The Planning Commission approved it in July 2025. More than a year later, the City still lists its construction plans as under review and its building permit as pending.
At 1521 E. Grand, even the size of the project keeps changing. A February 2025 environmental study described 323 apartments sponsored by Griffin Capital Catalyst Development Fund, LLC, and projected that construction would start in 2026. The City's pending list now shows 276 apartments on 3.617 acres with a 402-space garage, an incomplete application, and an EIR still being prepared. A project that hasn't settled on its unit count isn't close to breaking ground.
Say every stalled project started tomorrow. The new homes would still go up in the same few places, because that's where the City has decided growth belongs.
The rezoning that state law required is finished. El Segundo reports that it completed the rezoning on May 7, 2024, creating two high-density overlay zones and moving nine sites into Mixed-Use Overlay and Housing Overlay zones. The state Department of Housing and Community Development certified the Housing Element on July 15, 2024. In calendar year 2025, the City rezoned zero additional sites.
Downtown rules were set in the same year. The Downtown Specific Plan was adopted May 21, 2024 and took effect June 20, 2024. On Main Street it expects homes above or behind ground-floor businesses, with no density limit, a 30-foot height limit at the front property line, and 45 feet farther back. Richmond Street allows stand-alone residential up to 45 feet. The Grand Avenue District, which the plan calls its biggest redevelopment opportunity, allows 60 feet. The plan's market analysis projected demand for 200 to 375 downtown multifamily units through 2040. That figure is a demand forecast, not a cap.
The long-range plan follows the same lines. In its Vision 2050 General Plan update, the City brought land-use alternatives to the Planning Commission on September 24, 2026. The presentation for that session summarized the direction the City Council gave on October 21, 2025:
Downtown: off the table; settled through the new Specific Plan. Chevron/Refinery: off the table; City has no authority over the property. Residential neighborhoods: no appetite for density change.
The same deck says the alternatives were narrowed to underused corporate office land and areas next to Smoky Hollow. For Smoky Hollow, the draft options range from restoring and modestly expanding a medium-density residential overlay to adding mixed-use flexibility along its western edge or converting more of the overlay to mixed use. None of these has been adopted. The City's Vision 2050 page listed the next City Council study session for fall 2026 without a date.
The 2050 alternatives look for room on office land and near Smoky Hollow. The City Council expressed no appetite for density change in residential neighborhoods.
El Segundo's annual housing reports count two kinds of small-scale additions: accessory dwelling units, and SB 9 duplexes or lot splits. The numbers show how small that channel is. The City's 2025 Housing Element Annual Progress Report, presented to the City Council on March 3, 2026, recorded:
Nine finished ADUs in a year is real growth for a city this size, and permits are slowly going up. The neighborhoods change by a backyard cottage here and there.
Put the pieces together. The new homes the City has approved are almost all apartments. They're stalled on corridor sites. The 2024 rezoning is done, and no new sites were added in 2025. The long-range plan points future change at office land and Smoky Hollow. Inside the neighborhoods, the City reported nine ADU completions and no SB 9 units permitted in 2025.
The projects in the City's pipeline offer almost no new detached houses.
If you want newer construction in El Segundo, look at that corridor housing. Right now the City's records show six approved townhomes and six approved downtown homes, and neither project has started construction.
Is Pacific Coast Commons still approved? Yes. The City lists it as approved in 2022 with construction not yet started. A City contract record shows its development agreement current through April 19, 2037.
What did the City Council say about density in residential neighborhoods? The direction the Council gave in October 2025 said there was no appetite for density change in residential neighborhoods. The alternatives presented in September 2026 focus on office areas and Smoky Hollow. The plan hasn't been adopted, so check the City's Vision 2050 page for updates.
Can I add an ADU or use SB 9 on an El Segundo lot? The City's 2025 progress report counted 25 ADU permits and no SB 9 units. The rules that apply come from the state and the City, and the City's Housing Element page is the place to start. Whether either option works on a particular lot depends on that lot. This post is general information, not legal or financial advice. Confirm your own situation with the City's Planning Division and the right professionals.
If you're trying to buy a single-family home in El Segundo, it helps to know which listings are coming and what they're likely to sell for, because the projects in the City's pipeline offer almost no new detached houses. May-Ann Fisher follows El Segundo's resale market block by block and can help you build an offer strategy around that limited supply. Book a Consultation to talk through what's coming up.